-
All images on this page by Bob and Yvonne Hutton
-
- Drawing of how the CCG 107 will look
when the conversion is complete, deck plans arriving soon.
|
Now For Sale
|
- Preparation for Transportation - April/May 2001
-
- The CCG 107 was purchased from the Canadian Coast Guard in April
2001. Prior to this, her original diesels (Detroit 6v 53's with Borg
Warner 2.5-1 transmissions), shafts, propellers and many other items
were removed by the Coast Guard for spares.
-
- In order to prepare the 107 for the road trip to her new home, the
upper portion of the pilot house was removed as she was too tall due
to highway height restrictions. This was accomplished mainly with
the use of a skil-saw and a carbide non-ferrous metal blade (the Coast
Guard were kind enough to allow me the use of an electrical outlet).
This task took about 6 hours prior to the crane's arrival to lift
it off and fasten it to the foredeck for transport. With the major
work complete, all loose items were stored and the decks cleaned. An
environmental company was called in to pump the bilges free of oil
and sludge-contaminated water. Once the pre trip details were completed,
the crane and transport companies' schedules were finalized. A few weeks
later a 45 ton crane arrived to load the 107 on the low bed trailer
for the trip home. A second crane company was required to do the lift
at her destination.
|

- 09 May 2001
- CCG 107 on the low loader at her new home.
|
- Arrival - 09 May 2001
-
- A week prior to the 107's arrival 15 tons of 3/4 minus gravel was
imported to prepare a building pad for the specially designed cradle.
Once the gravel was levelled and compacted the cradle was assembled
and the site prepared. In order to facilitate the lift from the trailer
to the cradle, a 70 ton crane was required due to the distance and
the reach the crane would have to make. Due to circumstances, the
107's lifting eyes were unable to be inspected prior to delivery,
resulting in the use of slings and spreader bars for lifting. After
her 700 km long journey 107 arrived at her home ready for conversion
on the 09 May 2001. With the crane and low loader in place the spreader
bars and slings were attached ready for the lift. It took several
attempts to lift the boat with the slings, about 1 1/2 hours to adjust
them, (fortunately we had a lump sump quote for the service). Due
to the rubber D-bumpers the lifting slings would not slide freely
on the hull for a level lift. I would highly recommend using the lifting
eyes if at all feasible, as it is impossible to lift and place an
MLB on its cradle level, when the bumpers are in place and slings
are being used. As in this case, conversion of a boat which is not
level adds a substantial amount work to the process as all fitting
must be done through triangulation. For interest sake, at the time
of lift the crane's computer registered the 107's weight as 31,000
lbs.
|

- 09 May 2001
- Just prior to being lifted on to her specially designed
cradle.
|
- Removing Anti Foul - May 2001
-
- Our biggest task at hand was to stop the boat from rusting
any further, as we do not have covered or heated space to work.
-
- We started with below the water-line (for no particular reason)
removing all appendages, in this case intake screens and zinc's. If
you are going to do a proper job, you must remove all traces of rust.
I elected to blast it off, as it does a thorough job even in the pours
or pits of the corten steel hull. The zinc's were cut off with
a torch where their welding tabs met the hull (and there was lots
of them). You can see traces of them through their outline, on the
photo opposite below the waterline close to the bow. I also removed
the main engine intake screen and attempted to blast the inside but
as there are many ridges and baffles a decent job could not be done,
I ended up replacing the entire intake distribution box later in the
project due to corrosion problems.
|

- 13 May 2001
- Removing anti foul.
|
- Removing the Bumpers - May 2001
-
- In the photo opposite I am removing the bumpers. You can see the
rust which is concealed by them which is probably the biggest cause
of rust bleeding on theses boats. They were very difficult to remove
and I would bet darn near impossible to put back on. Probably why
this area does not get much attention, even in the 44's that are still
in service locally, you can see the stains. I have elected not
to reinstall them as they are in my opinion a seawater and corrosion
trap.
|

- 17 May 2001
- Grinding off the fastening studs getting ready to
blast the top half.
|
- Blasting on the upper hull - May 2001
|

- 23 May 2001
- Blasting on the upper hull.
|
- Fairing out the grind marks - June 2001
-
-
|

- 1 June 2001
- Fairing out the grind marks from the removal of
the bumper studs.
|
- Painting the numbers - July 2001
-
- .
|

- 22 July 2001
- Painting the numbers and water line.
|
- First coat of commercial marine paint - July 2001
-
-
|

- 29 July 2001
- First coat of commercial marine paint.
|
- Removing the pilot house - September 2001
-
|

- 2 September 2001
- Removing the pilot house.
|
| Removing the aft deck house and well-deck
- September 2001 |

- 18 September 2001
- Removing the aft deck house.
|
| Blasting out the inner hull - September 2001 |

- 20 September 2001
- Blasting out the inner hull.
|
| Inner hull just prior to applying the first
coat of epoxy - September 2001 |

- 21 September 2001
- Inner hull just prior to
applying the first coat of epoxy.
|
| Inner hull first coat of epoxy- September
2001 |

- 21 September 2001
- First coat complete.
|
| Getting 107 ready for winter - September
2001 |

- 23 September 2001
- Getting 107 ready for winter.
|
| Fitting the the prefabbed forward glass frame
- April 2002 |

- 28 April 2002
- Getting the the forward glass frame on deck and
in place.
|
| The arrival of the new engines - September
2002 |

- 5 September 2002
- The arrival of the new engines.
|
| Installing the new engines - September 2002 |

- 27 September 2002
- Installing the new engines.
|
| New engines ready for hook-up - September
2002 |

- September 2002
- New engines ready for hook-up.
|
| Berth - November 2002 |

- 11 November 2002
- View of berth after being stripped.
|
| Pilot house and galley - November 2002 |

- 11 November 2002
- View from pilot house to galley.
|
| Galley and pilot house - November 2002 |

- 11 November 2002
- View from galley to pilot house.
|
| Ready for winter - November 2002 |

- 20 November 2002
- Ready for winter.
|
| Sealing the scuppers - July 2003 |

- 19 July 2003
- Sealing the scuppers.
|
| Attaching the 3/16" mating plates -
August 2003 |

- 25 August 2003
- Attaching the 3/16" mating plate.
|
| Attaching the 1/8" deckhouse plating
- August 2003 |

- 25 August 2003
- Attaching the first piece of 1/8" deckhouse
plating.
|
| Final welding on deckhouse frames - September
2003 |

- 14 September 2003
- Welding on deckhouse frames.
|
| Preparing deckhouse frames for primer - September
2003 |

- 14 September 2003
- Preparing deckhouse frames for primer.
|
| Redesigning and installing the muffler system
- September 2003 |

- 21 and 25 September 2003
- Redesigning and installing the muffler system.
|
| Installing the superstructure plating - September
2003 |

- 25 September 2003
- Installing the superstructure plating.
|
| Welding aft deck - October 2003 |

- 14 October 2003
- Welding aft deck.
|
| Galley primed ready for insulation - November
2003 |

- 11 November 2003
- Galley primed ready for insulation.
|
| Insulating hull and cabins - November 2003
|

- 11 November 2003
- Left - insulating aft deckhouse. Right - insulating
hull.
|
| Ready for another winter - November 2003 |

- 15 November 2003
- Ready for winter.
|
| Leaving New Brunswick - April 2004 |

April 2004
Leaving New Brunswick |
| At North Western Ontario - September 2005 |

September 2005
At North Western Ontario |
|
Home

|